The Conversations Nobody Wants
Part of Clinical Project Management (PM) Training: Sponsor Communication and Escalation.
About 1 minutes. Free, in your language, no account needed.
Four that project managers delay, and what delay costs
Telling a site it is being closed. Delay means more months of drug on a shelf, monitoring attention spent for no data, and a harder conversation later.
Telling the sponsor a date will not be met. Delay means the sponsor plans, communicates and sometimes commits externally against a date you already knew was gone.
Telling a vendor their service is not acceptable. Delay means the evidence gets older and the relationship harder to correct.
Telling your own team a plan has changed. Delay means people keep working on the old plan, which is waste and also disrespect.
What makes them easier
Facts rather than characterization. "Three of the last four data transfers were late, by six, nine and four days" is a conversation. "Your quality has been poor" is an argument.
A clear ask. What you need to change, by when, and what happens if it does not.
Written follow-up, the same day, saying what was agreed. Not as a threat, but because memory diverges and the file is what survives.
Assume good faith and act on evidence
Most underperformance is capacity or comprehension, not indifference. Starting from that assumption gets you a truthful answer far more often, and the evidence still constrains what happens next if the answer turns out to be indifference.
The record protects everyone, including the person on the other side of the conversation.